SU Logo
SU Logo
True
home  > Our Community > Construction Project Updates
Construction Project Updates
Select a project to view the status updates. Please note that only Stoughton Utilities lead projects that have a significant impact on residents are listed. For more information about any past, ongoing, or planned construction projects, please contact us.
  
2019 Street & Utility Construction
Updates on Current Stoughton Utilities Construction Projects
Monday, June 24, 2019
Week 6 Construction Update
Work completed for the 6th week: 6/17 thru 6/21
  • Contractor started sanitary sewer lateral replacements along Monroe Street between the Lowell and Oak Street intersections on Monday.
  • Crews also de-chlorinated the new water main on Monday.
  • Water main samples were taken Tuesday morning. Safe water samples were obtained on Thursday morning.
  • Water main pressure testing was completed Thursday.
  • Crews started with sanitary sewer and water service replacements on Lowell Street between the Monroe and Prairie Street intersections on Thursday and continued through midday on Friday.
  • The contractor spent the remainder of the workday on Friday performing site and erosion control cleanup.
  • Intercon has completed gas main and service relocations along Patterson and the North portion of Monroe Street. A portion of their relocation effort at the Main Street and South Harrison Street intersection will be completed once the project utility work under Stage 3 has occurred.
Work Anticipated for the 7th week: 6/24 thru 6/28
  • Contractor to continue with sanitary sewer lateral and water service replacements along Lowell Street between the Monroe and Page Street intersections as well as Monroe Street between the Lowell and Oak Street intersection.
  • Contractor to provide 24 HR notification to residents ahead of water service replacements or outages.
  • A second utility crew is expected to arrive during the later part of the workweek.
  • Contractor to begin installation of storm sewer on Lowell Street once the water services and sanitary sewer laterals have been completed between the Prairie and Page Street intersection.
 
Monday, June 17, 2019
Week 5 Construction Update
Work completed for the 5th week: 6/10 thru 6/14:
    Contractor continued with water main installation on Lowell Street working West towards the Monroe Street intersection starting on Monday.Crews reached the Monroe Street intersection Monday afternoon and began water main installation on Monroe Street working North towards the Oak Street intersection.Water main installation on Monroe Street was completed to the new fire hydrant located on the North side of the Monroe and Oak Street intersection by Thursday morning. Pipe crews installed the new fire hydrant located in front of the 734 Monroe Street property Thursday afternoon.The relocated fire hydrant located at the Southwest corner of the Lowell and Page Street intersection on Friday morning.The newly installed water main was filled on Friday afternoon and will remain chlorinated through the weekend.
Work Anticipated for the 6th week: 6/17 thru 6/21:
  • Contractor to flush chlorinated water main on Monday.
  • Water samples will be taken and results should be obtained by Tuesday. After safe water samples are obtained and provided to owner contractor will conduct hydrostatic pressure testing of new water main.
  • Contractor to start with sanitary sewer lateral and water service replacements along Lowell Street between the Monroe and Page Street intersections as well as Monroe Street between the Lowell and Oak Street intersection. Contractor to provide 24 HR notification to residents ahead of water service replacements or outages.
  • Intercon to continue with gas main and service relocations along Patterson and the North portion of Monroe Street.
 
Monday, June 10, 2019
Week 4 Construction Update
Work completed for the 4th week: 6/3 thru 6/7
  • Contractor continued with water main installation on Lowell Street working West towards the Monroe Street intersection starting on Monday and continued through the week to Friday.
  • Crews installed the new fire hydrants near the 401 and 525 Lowell Street properties.
  • No water services or sanitary lateral work was completed this week.
Work Anticipated for the 5th week: 6/10 thru 6/14
  • Contractor to resume water main installation at the Lowell and Monroe Street intersection on Monday.
  • Water main installation on Monroe Street will commence South towards the Oak Street intersection for the early portion of the workweek.
  • Water main disinfection, flushing, and sampling will occur after the Stage 1 limits of water main and fire hydrants have been installed.
  • Water service reconnections will be scheduled once safe water samples have been received and hydrostatic pressure testing has been completed.
  • Intercon to continue with gas main and service relocations along Patterson and the North portion of Monroe Street.
 
Monday, June 03, 2019
Week 3 Construction Update
Work completed for the 3rd week: 5/27 thru 5/31
  • No work on 5/27. Memorial Day observed.
  • Contractor continued with sanitary sewer installation working West along Lowell Street on 5/28. Crews reached the Monroe Street intersection early Monday Tuesday morning.
  • Sanitary sewer installation then continued North along Monroe Street working towards the Oak Street intersection.
  • By Thursday morning the sanitary sewer installation was completed to MH San-6, which is located just South of the Oak Street intersection.
  • Thursday afternoon the contractor installed the North stub of sanitary sewer out of MH San-2 at the Lowell and Prairie Street intersection.
  • Contractor installed a water service Thursday afternoon. The new service is located just North of the Milwaukee and Monroe Street intersection. The new service is intended replace an existing long service that currently serves 1 singe home and 3 duplex homes along Milwaukee Street. The existing service connects in the Monroe and Lowell intersection and is to be abandoned.
  • Contractor started water main installation on Lowell Street intersection by making the connection near the Page Street intersection on 5/31. Water outage coordinated with Stoughton Utilities.
  • Water main installation continued West along Lowell Street working towards the Prairies Street intersection.
  • Intercon was present on Monroe and Lowell Street performing restoration associated with the previous weeks of gas main and service relocations.
Work Anticipated for the 4th week: 6/3 thru 6/7
  • Contractor to resume water main installation along Lowell Street working West towards the Monroe Street intersection.
  • Water main installation on Lowell Street to continue for a majority of the workweek.
  • Water main installation on Monroe Street between the Oak and Lowell Street intersection could possibly start later in the workweek.
  • Intercon to begin gas main and service relocations along Patterson and the North portion of Monroe Street sometime next week.
 
Thursday, May 30, 2019
Week 1 & 2 Construction Update
Work completed for the 1st & 2nd week:
5/13/2019 through 5/17/2019
5/20/2019 through 5/24/2019
  • Contractor mobilized material and equipment to the Stage 1 project limits of Monroe and Lowell Street on 5/13.
  • Contractor started sanitary sewer installation on Lowell Street on 5/14. Work began at the Page Street intersection and continued with sanitary sewer installation working West along Lowell Street.
  • By the end of the day on 5/17 the sanitary sewer mainline installation was completed to Sta. 15+67.
  • Intercon was present on Monroe Street performing gas main and service relocations between the Lowell and Main Street intersections.
  • Contractor continued with sanitary sewer installation working West along Lowell Street on 5/20.
  • By the end of the day on 5/23 the sanitary sewer mainline installation was completed to Sta. 10+78.
  • Two separate water main breaks occurred on 5/21 near Sta. 14+65 on Lowell Street. Stoughton Utilities responded to both incidents to provide outage to allow for the contractor to make the necessary repairs.
  • No work occurred on 5/24 due to rain. Contractor onsite to perform cleanup ahead of the weekend.
  • Intercon was present on Monroe Street performing gas main and service relocations between the Lowell and Main Street intersections. By the end of the workweek, crews had finished the remaining relocations in the Stage 2 work area.
Work Anticipated for the 3rd week: 5/27 thru 5/31
  • No work planned for 5/27. Memorial Day observed.
  • Contractor to resume sanitary sewer installation at the Monroe and Lowell Street intersection. Sanitary sewer installation to begin on Monroe Street and continue North towards Oak Street.
  • Sanitary sewer mainline work to be completed by the middle part of the workweek.
  • Contractor to begin water main installation on Lowell Street in the later part of the week. A connection date near the Page Street intersection and the associated outage on Lowell Street will be coordinated with Stoughton Utilities. Contractor to provide notification to residents.
  • Intercon was present on Monroe Street completing terrace restoration along Monroe, Lowell, and Milwaukee Street. They intend to begin gas main and service relocations on Patterson Street and Monroe Street (North of Main Street) near the end of the work week.
 
top