SU Logo
SU Logo
true
home  > Our Community > Construction Project Updates
Construction Project Updates
Select a project to view the status updates. Please note that only Stoughton Utilities lead projects that have a significant impact on residents are listed. For more information about any past, ongoing, or planned construction projects, please contact us.
  
2018 Street and Utility Construction - Forrest, Gjertson, Vernon, Franklin
Updates on Current Stoughton Utilities Construction Projects
Monday, September 10, 2018
Week 16 Project Update
Work completed for the week of: 9/3/18-9/7/18
  • Monday – No work today, holiday.
  • Tuesday – No work today.
  • Wednesday – Crew on site to remove marked curb in preparation for curb to be poured later this week before surface paving Saturday.
  • Thursday – Contractor on site to pour remaining curb sections and driveways on Franklin Street. Contractor placing traffic control in preparation for Saturday paving.
  • Friday – Crew on site finishing landscaping. Tri-County on site to mill binder around manholes and some areas near curb along with general sweeping of road of any debris before paving.

Work Anticipated for the week of: 9/10/18-9/14/18
  • The contractor will do a general cleanup of the site, repair curb sections, ramp the manholes with cold patches along with other miscellaneous work that needs to be done before final paving. Final paving is scheduled for September 8th (Saturday) to avoid school traffic. All other work will be completed by this time. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Tuesday, September 04, 2018
Week 15 Project Update
Work completed for the week of: 8/27/18-8/31/18
  • Monday – Crew on site to continue setting manhole castings in preparation for binder paving Wednesday. Proof roll of Morris and Henry Street were done and undercutting curb edges was needed.
  • Tuesday – The crew on site prepping Franklin St patches for binder paving Wednesday. Finishing fine grading from Henry Street to end of Vernon to the east. All-Ways on site to start restoration (topsoil, seed, and mulch).
  • Wednesday – Crew on site to clean up the washouts from the rain last night before paving starts. Tri-County on site to pave binder on Vernon St and patches on Franklin St.
  • Thursday – All-Ways on site to complete the restoration work.
  • Friday – No work done today.

Work Anticipated for the week of: 8/3/18-8/7/18
  • The contractor will do a general cleanup of the site, repair curb sections, ramp the manholes with cold patches along with other miscellaneous work that needs to be done before final paving. Final paving is scheduled for September 8th (Saturday) to avoid school traffic. All other work will be completed by this time. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Monday, August 27, 2018
Week 14 Project Update
Work completed for the week of: 8/20/18-8/24/18
  • Monday – Cattell on site to complete the remaining concrete work, east end of Vernon and Kristi Ln driveways and some sidewalk/aprons. Contractor on site to continue placing black dirt on Vernon/Kristi. Crew worked through rain, started at 12:45 pm.
  • Tuesday – The crew continued to place black dirt on Vernon Street. Starting to fine grade on Vernon Street starting at Academy Street going east.
  • Wednesday – Crew removing excess dirt on south end of Kristi Ln, installing the 18” corrugated metal pipe culvert extension on south end of Kristi Ln. Base course placed in the turnaround at the end of Kristi Ln. Crew then installed overflow swale between 1203/1109 Vernon Street per plan.
  • Thursday – The crew continued placing base course on Kristi Ln, completing placement of black dirt on Kristi Ln. Crew continued to fine grade on Vernon Street and Kristi Ln. Manhole and water valve adjustments were started.
  • Friday – Crew continued to fine grade Kristi Ln and Vernon Street that was not completed yet. Crew completing adjustments for manholes and water valves in preparation for paving next week.

Work Anticipated for the week of: 8/27/18-8/31/18
  • The contractor will finish up fine grading and clean the site in preparation for paving early in the week. Placement of binder is tentatively scheduled for Tuesday (8/28), will need to get a schedule from contractor when they hear back from subcontractors. Landscapers are scheduled to be on site next week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Friday, August 17, 2018
Week 13 Project Update
Work completed for the week of: 8/13/18-8/17/18
  • Monday – The utility crew on site to continue water service installation at 917 Nelson St. Removed hydrant at SW corner of South St and Franklin St and installed new hydrant at NW corner of the intersection. Retaining wall starting at 224 S Franklin, concrete forms being set for sidewalk pour Wednesday.
  • Tuesday – The utility crew was on site completing water main work on S Franklin St including abandoning old water main on Franklin St.
  • Wednesday – Cattell on site to pour sidewalk on the remaining portion of Vernon including driveway aprons on Kristi Ln. Contractor placing black dirt in the terraces on Vernon starting at Academy Street and working east.
  • Thursday – The crew continued placing black dirt along Vernon Street. Retaining wall complete at 224 S Franklin St.
  • Friday – Crew started to grade yards on Kristi Ln, stopped due to too much rain.

Work Anticipated for the week of: 8/20/18-8/24/18
  • The contractor will continue placing black dirt in terraces, grading yards to plan and installing the swale between 1203 and 1109 Vernon Street. Cattell will pour the remaining areas that need to be completed. Landscapers scheduled to be on site next week to start seeding terraces and yards. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Monday, August 13, 2018
Week 12 Project Update
Work completed for the week of: 8/3/18-8/10/18
  • Monday – No work today due to rain.
  • Tuesday – The utility crew was on site continuing water service installation at 225 Henry and 307 Franklin St.
  • Wednesday – The utility crew continued water services on Franklin Street; 308, 311, 307, and 316 Franklin St installed. Cattell on site pouring the remaining curb on Vernon Street and Kristi Ln.
  • Thursday – The utility crew continued installing water services on Franklin Street; 325, 320, and 324 Franklin installed.
  • Friday – The utility crew continued installing water services on Franklin Street; 925 Nelson and 414/416 Franklin installed.

Work Anticipated for the week of: 8/6/18-8/10/18
  • The contractor will complete water services on Franklin Street including the water main extensions and hydrant work needed on Franklin St/South St. Cattell will be pouring the remaining sidewalk and driveway aprons midweek on Vernon Street. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, August 08, 2018
Week 11 Project Update
Work completed for the week of: 7/30/18-8/3/18
  • Monday – The utility crew was onsite continuing subgrade work on Kristi Ln. Cattell on site to install forms for sidewalk installation Wednesday.
  • Tuesday – The utility crew completed subgrade work on Kristi Ln and Kristi/Vernon St intersection. Cattell on site continuing installation of forms for sidewalk and ramps pour Wednesday.
  • Wednesday – The utility crew repaired sanitary sewer wye at manhole in between 1203 Vernon and 1109 Vernon property. Cattell on site pouring sidewalk on Vernon Street.
  • Thursday – The crew installing underdrain at low point inlets and adjusting inlet castings. Cattell on site completing the ramp and driveway pours.
  • Friday – Crew on site installing water services on Henry Street.

Work Anticipated for the week of: 8/6/18-8/10/18
  • The contractor will continue water services on Henry Street along with grading out a swale between 1203 and 1109 Vernon properties. Cattell will be pouring the remaining curb midweek and possibly pouring remaining sidewalk later in the week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Monday, July 30, 2018
Week 10 Project Update
Work completed for the week of: 7/23/18-7/27/18
  • Monday – The utility crew was onsite to start installation of water services on Kristi Ln. A second utility crew installed underdrain at low point inlets on Morris/Vernon Street intersection. Cattell on site to put up stringline in preparation for curb on Wednesday.
  • Tuesday – The utility crew completed installation of the water services on Kristi Ln. The crew then continued to install storm sewer at Kristi Ln/Vernon St intersection. Cattell on site to grade for curb Wednesday.
  • Wednesday – The utility crew completed the storm sewer work at Kristi Ln intersection. Cattell on site to pour curb from Academy Street to just west of Henry Street.
  • Thursday – The crew was on site to start removing curb, gutter, and remaining asphalt on Kristi Ln and Vernon Street west of Henry Street.
  • Friday – Crew on site to start subgrade work on Vernon Street from Henry Street towards Kristi Ln. Crew subgrade from Henry Street intersection to just east of Kristi Ln.

Work Anticipated for the week of: 7/30/18-8/3/18
  • The contractor will continue subgrade work on Vernon Street and Kristi Ln. Cattell will be onsite to pour sidewalk early in the week. The contractor will prepare Vernon Street and Kristi Ln for curb the following week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Friday, July 20, 2018
Week 9 Project Update
Work completed for the week of: 7/16/18-7/20/18
  • Monday – The utility crew was on site to start installing 8” watermain on Kristi Ln. Crew installed north hydrant on Kristi Ln and Vernon Street intersection. A second crew was on site to continue subgrade work and removals of sidewalk and curb on Vernon Street from Morris Street to Henry Street.
  • Tuesday – The utility crew completed installation of water main on Kristi Ln including the south hydrant. A second utility crew was on site to start installing storm sewer at Morris Street and Vernon Street intersection.
  • Wednesday – The utility crew was on site to continue storm sewer work at Morris Street intersection. Once completed, the crew started to install inlets at Henry Street. A second utility crew started to install storm sewer on Vernon Street proceeding east towards Kristi Ln.
  • Thursday – The utility crew continued storm sewer work on Vernon St towards Kristi Ln. A second crew continued subgrade work on Vernon Street from Morris St to Henry in preparation for curb on Monday or Tuesday next week.
  • Friday – No work due to rain.

Work Anticipated for the week of: 7/23/18-7/27/18
  • The contractor will start installing water services along Kristi Ln, and continuing storm sewer at Kristi Ln intersection. Crew will continue subgrade work from Henry Street to Kristi Ln and up Kristi Ln. Curb will be poured on Vernon Street from Academy Street to Henry Street early in the week. Sidewalk to be poured later in the week where curb was poured. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Monday, July 16, 2018
Week 8 Project Update
Work completed for the week of: 7/9/18-7/13/18
  • Monday – The utility crew continued to work on installing new water services and sanitary laterals for 1017, 1025, and 1033 Vernon Street. A second crew was on site to continue subgrade work on Vernon St from Academy to Morris St.
  • Tuesday – The utility crew continued to work on installing new water services and sanitary laterals for 1101 Vernon, 225 Morris, and 220 Henry St. A second crew was on site to continue subgrade work on Vernon St from Academy to Morris St.
  • Wednesday – Both crews were on site continuing removals of sidewalk and curb and gutter along with asphalt. The crews continued to grade Vernon from Academy to Morris St.
  • Thursday – The utility crew installed the new water main on Morris Street including a new hydrant on the NE corner of Vernon and Morris St. intersection.
  • Friday – The utility crew was onsite to install two new water main tees on Vernon Street. The crew also installed a 6”valve for the new hydrant on Henry St intersection along with a new 8” valve to install new water main on Kristi Ln.

Work Anticipated for the week of: 7/16/18-7/20/18
  • The contractor will continue with installation of water main on Kristi Ln and installation of the new hydrant on Henry St intersection. The crew then will start work on storm sewer along Vernon Street. A second crew will continue road work and possible placement of curb and gutter and sidewalk from Academy Street to Franklin Street late in the week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Tuesday, July 10, 2018
Week 7 Project Update
Work completed for the week of: 7/2/18-7/6/18
  • Monday – Tri-County on site to pave both binder and surface on Gjertson and Forrest Street. Both streets still closed to ensure that the asphalt cools before traffic is allowed. Utility crew was started sanitary work on Henry Street from the Vernon Street intersection north to the new manhole.
  • Tuesday – The utility crew continued work on Henry Street and installed new manhole. Once manhole was placed, crew started to install the new water services on Vernon Street.
  • Wednesday – Holiday, no work.
  • Thursday – The utility crew installed the sanitary sewer on Morris Street. A second crew was on site to start grading Vernon Street from Academy to Franklin. Guidelines was on site to paint the pavement markings on Gjertson and Forrest Street.
  • Friday – The utility crew continued to install water services and sanitary laterals along Vernon Street. The grading crew installed stop signs on Gjertson and Forrest Street. Landscapers on site to place topsoil and seed in areas that washed out. Both roads open to traffic.

Work Anticipated for the week of: 7/9/18-7/13/18
  • The contractor will continue work on Vernon Street with installation of water services and sanitary laterals. Grading crews will continue to grade the west end of Vernon Street. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Sunday, July 01, 2018
Week 6 Project Update
Work completed for the week of: 6/25/18 - 6/29/18
  • Monday – The contractor was on site on Vernon starting to install sanitary sewer from the Henry Street intersection west. Cattell was on site to pour the concrete driveway aprons and colored concrete ramps on Forrest Street.
  • Tuesday – The contractor was on site on Vernon Street continuing to install sanitary sewer and also flushed and took a water sample of the water main that was installed last week (6/19). A second crew was on site on Gjertson Street starting to install the retaining wall on the north end of the street.
  • Wednesday – The utility crew continued to install sanitary sewer on Vernon Street. Cattell was on site on Forrest pouring the concrete tree grates, concrete terrace, and concrete burb for the new railing next to the hair salon. The wall crew continued to install the retaining wall on Gjertson Street.
  • Thursday – The utility contractor continued to install sanitary sewer on Vernon Street. Cattell was on site pouring the remaining colored concrete on Forrest Street. A second crew was on Forrest Street adjusting castings and grading the South Alley in preparation for paving on Monday (7/2). The landscapers were on site on both Forrest and Gjertson Street placing seed, topsoil and mulch. The wall crew continued to install the retaining wall.
  • Friday – The utility crew completed the sanitary sewer on Vernon Street. The second crew fine graded and proof rolled Forrest Street/South Alley in preparation for paving on Monday. The crew then started fine grading on Gjertson Street in preparation for paving Monday (7/1). The landscapers were on site on both Forrest and Gjertson Street placing seed, topsoil and mulch. The wall crew completed the retaining wall on Gjertson.
    Will work tomorrow (6/30) to complete the fine grading and proof roll of Gjertson Street.

Work Anticipated for the week of: 7/2/18-7/6/18
  • Paving both the binder and surface is scheduled for Monday (7/2) for both Forrest and Gjertson Street. Pavement striping is scheduled for later in the week.
  • The contractor will continue work on Vernon Street with installation of sanitary sewer on Henry Street and Morris Street. Once that is complete, the crew will start to install the new water services on Vernon Street. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Thursday, June 28, 2018
Week 5 Project Update
Work completed for the week of: 6/18/18 - 6/22/18
  • Monday – Contractor on site at Vernon Street installing water main starting at the Academy Street intersection and working east. Cattell on site on Gjertson Street to finish pouring sidewalk and form the 24” valley gutter near Dollar General.
  • Tuesday – No work due to rain.
  • Wednesday – Contractor on site to continue installing 8” watermain on Vernon Street. Cattell on site to form sidewalk on Forrest Street in preparation to pour sidewalk on Friday (6/22).
  • Thursday – No work on Vernon Street or Forrest Street due to rain. Crew on site at Gjertson Street to adjust the sanitary manhole.
  • Friday – Contractor on site to continue 8” water main on Vernon Street. Cattell on site to pour the sidewalk and ramps on Forrest Street as well as some of the area by Dollar General on Gjertson Street.
  • Saturday – Cattell on site to continue pouring on Forrest Street and complete the pour on Gjertson Street near Dollar General.

Work Anticipated for the week of: 6/25/18-6/29/18
  • The contractor will pour colored concrete at Forrest Street early in the week along with driveway aprons on Forrest Street. The retaining wall on Gjertson Street is anticipated to be installed early to middle of the week. Contractor will continue to fine grade on Gjertson Street and Forrest Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will continue work on Vernon Street with sanitary sewer starting at the Henry Street intersection heading west along Vernon. The crew will be removing asphalt and parts of the curb and gutter while installing the sanitary sewer. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Monday, June 18, 2018
Week 4 Project Update
Work completed for the week of: 6/11/18 - 6/15/18
  • Monday – The contractor formed sidewalk on Gjertson Street in preparation for sidewalk pouring later in the week. A second utility crew was placing traffic control and starting to strip asphalt on Vernon Street.
  • Tuesday – The contractor was on site at Forrest Street adjusting inlet castings in preparation for curb being poured on Wednesday. The second utility crew started sanitary installation on Vernon Street.
  • Wednesday – Curb was poured on Forrest Street and some sidewalk poured on Gjertson Street. The second utility crew continued to install new sanitary sewer on Vernon Street.
  • Thursday – Contractor on site at Gjertson Street finishing forming the sidewalk. The second utility crew continued to install new sanitary sewer on Vernon and Franklin Street.
  • Friday – No work on Gjertson Street. The second utility crew completed sanitary sewer on Franklin Street.

Work Anticipated for the week of: 6/18/18-6/22/18
  • The contractor will pour sidewalk, driveway aprons, and curb ramps early to middle of the week on Gjertson Street. Sidewalk and driveway aprons are anticipated to be poured later in the week on Forrest Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will continue work on Vernon Street with water main starting at the Academy Street intersection. The crew will be removing asphalt and parts of the curb and gutter while installing water sewer starting at the Academy Street intersection. Sanitary sewer will be continued on Vernon Street near the Henry Street intersection later in the week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, June 13, 2018
Week 3 Project Update
Work completed for the week of: 6/4/18 - 6/8/18
  • Monday – The contractor completed subgrade work on Gjertson Street. A second utility crew continued to work on subgrade work on Forrest Street.
  • Tuesday – The contractor completed the curb basecourse work Gjertson Street in preparation for curb to be poured on Thursday. A second utility crew installed the last inlet and continued with subgrade work on Forrest Street.
  • Wednesday – Final grading on Gjertson Street in preparation for curb. A second crew was on Forrest Street completing the concrete removals near Main Street.
  • Thursday – Curb was poured on Gjertson Street.
  • Friday – No work on Gjertson Street. A crew continued basecourse work on Forrest Street.

Work Anticipated for the week of: 6/11/18-6/15/18
  • The contractor will pour sidewalk, driveway aprons, and curb ramps early to middle of the week on Gjertson Street. Curb and gutter is anticipated to be poured later in the week on Forrest Street. Continuing of basecourse work on Forrest Street. Access will be restored at the end of each work day.
  • The contractor will start work on Vernon Street on Monday. The crew will be removing asphalt and parts of the curb and gutter while installing sanitary sewer starting at the Academy Street intersection. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, June 06, 2018
Week 2 Project Update
Work completed for the week of: 5/29/18 - 6/1/18
  • Monday – No work, Memorial Day.
  • Tuesday – The contractor started subgrade work on Gjertson Street. A second utility crew continued with sanitary sewer installation in the alley on Forrest Street.
  • Wednesday – No work, rain day.
  • Thursday – The contractor continued with subgrade work on Gjertson Street. The second crew completed storm sewer installation on Forrest Street.
  • Friday – The contractor continued subgrade work on Gjertson Street. The second utility crew started subgrade work on Forrest St.

Work Anticipated for the week of: 6/4/18-6/8/18
  • The contractor will continue subgrade work on both Gjertson Street and Forrest Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will start grading curb and gutter on both Gjertson and Forrest Street. Curb and gutter is anticipated to be early in the week on Gjerston Street and late in the week on Forrest St. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, June 06, 2018
Week 1 Project Update
Work completed for the week of: 5/21/18 - 5/25/18
  • Monday – The contractor mobilized to both the Gjertson and Forrest Street project areas. Traffic control and erosion control devices were provided. The contractor performed pavement removals on both streets ahead the next days anticipated utility work.
  • Tuesday – The contractor started with storm sewer installation on Gjertson Street. A second utility crew started with sanitary sewer installation on Forrest Street.
  • Wednesday – The contractor continued with storm sewer installation on Gjertson Street. The second crew continued with sanitary sewer installation on Forrest Street.
  • Thursday – The contractor continued with storm sewer installation on Gjertson Street and installed the new Fire hydrant on the South end of Gjertson Street. The second crew continued with sanitary sewer installation on Forrest Street. Much time was devoted to the installation of sanitary sewer extending East into the alley East of Forrest Street. The excavation and crossing of the many utilities in this area complicated the work.
  • Friday – The contractor on Gjertson Street started installation of the new water service and sanitary sewer laterals to the 208 Van Buren Street property. They also performed the lowering of the existing water service for the 117 Gjertson Street property. The second utility crew continued with sanitary sewer installation in the alley East of Forrest Street.

Work Anticipated for the week of: 5/28/18-6/1/18
  • The contractor will start subgrade work on Gjertson Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will continue with sanitary sewer installation in the alley East of Forrest Street. Storm sewer installation at the Forrest and Jefferson Street intersection will begin early in the week followed with the start of subgrade work later in the week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
top