SU Logo
SU Logo
true
home  > Our Community > Construction Project Updates
Construction Project Updates
Select a project to view the status updates. Please note that only Stoughton Utilities lead projects that have a significant impact on residents are listed. For more information about any past, ongoing, or planned construction projects, please contact us.
  
2017 Street and Utility Construction
Updates on Current Stoughton Utilities Construction Projects
Wednesday, August 23, 2017
Construction Update - Week 18
Work completed for the week of: 8/14/17 – 8/18/17
  • Monday – The general contractor continued with sewer lateral and water service replacements on Brickson and Manilla Street. The concrete subcontractor poured curb and gutter on Division Street.
  • Tuesday – The general contractor continued with sewer lateral and water service replacements on Brickson and Manilla Street. The concrete subcontractor had sidewalk form crews present setting forms. Forest had a crew assisting with sidewalk grade preparation on Division Street.
  • Wednesday – The general contractor continued with sewer lateral and water service replacements on Brickson and Manilla Street. The concrete subcontractor had sidewalk form crews present setting forms and completing sidewalk and apron pours. Forest had a crew assisting with sidewalk grade preparation on Division Street.
  • Thursday – The general contractor completed the water main tie connection near the Brickson and Page Street intersection. After the completion of the water connection crews began installation of storm sewer on Brickson Street.
  • Friday – The general contractor continued with storm sewer installation on Brickson Street. The concrete subcontractor had sidewalk form crews present setting forms and completing sidewalk and apron pours.

Work Anticipated for the week of: 8/21/17-8/25/17
  • Harrison, Park/Lynn, and Henry/Giles
    • Surface paving is schedule to start on August 30th and 31st.
  • Division Street
    • Sidewalk and apron pours will be completed by Tuesday.
    • Terrace grading and restoration crews will be present later starting on Thursday the 24th and will likely run through the Monday 28th.
    • Road grading on Division Street will start on August 29th.
    • Binder paving is scheduled to occur on August 30th. Surface paving will occur the following day on the 31st.
    • Street work and restoration to be completed and open on September 1st.
  • Brickson/Manilla Street
    • Utility crews will finish the remaining storm sewer by Tuesday.
    • Road grading crews will begin subgrade work by Wednesday.
    • Curb and gutter pours is expected during the week of the 28th.
  • Milwaukee Street
    • Utility crews may mobilize to project area later in the week to start with water main installation.
 
Tuesday, August 15, 2017
Construction Update - Week 17
Work completed for the week of: 8/7/17 – 8/11/17
  • Monday – The general contractor continued with water main installation on Brickson Street. Crews completed the water main up to the connection near the Page Street intersection. The subgrade crew continued with road building efforts on Division Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.
  • Tuesday – The general contractor started with sanitary sewer installation on Brickson Street. The subgrade crew continued with road building efforts on Division Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Road crews excavated and abandoned an inactive water service and curb stop. A second utility crew replaced a water service at the Division and North Street intersection.
  • Wednesday – The general contractor continued with sanitary sewer installation on Brickson Street. Crews completed the sanitary sewer mainline installation after installation of a new manhole near the Page Street intersection. The subgrade crew continued with road building efforts at the North and Division Street intersection. The remaining subgrade work was completed by the end of the day.
  • Thursday – The general contractor started with sewer lateral and water service replacements on Brickson Street. The concrete subcontractor setup stringline intended for curb pours on Division Street.
  • Friday – The general contractor continued with sewer lateral and water service replacements on Brickson Street. The crew adjusted storm sewer inlets in the morning while the concrete subcontractor performed curb grading and preparation.

Work Anticipated for the week of: 8/14/17-8/18/17
  • Harrison, Park/Lynn, and Henry/Giles
    • Paving is not intended to occur until later this August.
  • Division Street
    • Curb and gutter will be poured on Monday. Sidewalk and driveway apron pours will occur throughout the remainder of the week.
  • Brickson/Manilla Street
    • Utility crews will continue with water service and sewer lateral replacements early in the week.
    • Utility crews will start installation of storm sewer on Brickson Street.
  • Milwaukee Street
    • Utility crews may mobilize to project area later in the week to start with water main installation.
 
Monday, August 07, 2017
Construction Update - Week 16
Work completed for the week of: 7/31/17 – 8/4/17
  • Monday –The general contractor started with water main installation on Mannila Street. A connection was made near the Forton Street intersection and utility crews continued with water main installation working South along Manilla Street.
  • Tuesday – The general contractor continued with water main installation working South along Manilla Street. The subgrade crew started with road building efforts on Division Street. They began work near the City boathouse on Division Street and worked south towards the Forton Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.
  • Wednesday – The general contractor switched to sanitary sewer installation on Manilla Street. A connection to the existing sanitary sewer manhole midblock on Manilla Street occurred early in the morning. Crews were able to complete the main installation after connected to the existing sanitary sewer manhole near the Forton Street intersection. The subgrade crew continued with road building efforts on Division Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.
  • Thursday – The general contractor continued with water main installation on Manilla Street. Crews were able to install the new fire hydrant at the Northeast corner of the Manilla and Brickson Street intersection and ended the day once reaching the Brickson Street intersection. A second utility crew also completed the water main connection at the Division and North Street intersection. The subgrade crew continued with road building efforts on Division Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.
  • Friday – The general contractor continued with water main installation on working West along Brickson Street. A second utility crew completed the installation of the remaining storm sewer inlets and piping at the Division and North Street intersection. They also completed the abandonment of an existing fire hydrant near the same intersection. The subgrade crew continued with road building efforts on Division Street and roadway was completed to the North Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.

Work Anticipated for the week of: 8/7/17 – 8/11/17
  • Harrison, Park/Lynn, and Henry/Giles
    • Paving is not intended to occur until later this August.
  • Division Street
    • Subgrade crews will continue with road building efforts. Work is expected to occur from the North Street intersection to the Washington Street intersection. Crews will be excavating roadway and placing gravel. Access to driveways will be difficult during daytime activities. Alternative off project parking should be anticipated. Access to driveways will be restored at each days end.
    • Curb and gutter is tentatively in the schedule for the later part of the week. Notification will be provided to residents ahead of this effort.
  • Brickson/Manilla Street
    • Utility crews will continue with water main work followed by sanitary sewer replacement on Brickson Street throughout the early part of next week. After sampling and testing it is anticipated that water service and sewer lateral work will occur during the later part of the week.

 
Wednesday, August 02, 2017
Construction Update - Week 15
Work completed for the week of: 7/24/17 – 7/28/17
  • Monday –The general contractor continued with storm sewer installation on Division Street by installing Inlets 8.1, 8.2, and 8.3. Once finished with the series 8 storm sewer structures they began with installation of AEW-2 and the storm sewer leading towards the Division Street intersection.
  • Tuesday – The general contractor continued with storm sewer installation on Division Street by installing inlet MH SS-6. After installation of the inlet, they spent the remainder of the day performing restoration of the park areas disturbed by the new outfall installation.
  • Wednesday – The general contractor started with water main installation in the Division and North Street intersection. The water main installation included a new fire hydrant and a offset connection for future use on North Street. The landscaping subcontractor was present on the Henry and Giles Street project area performing terrace restoration.
  • Thursday – The general contractor continued with storm sewer installation in the Division and North Street intersection. There was an elevation conflict between the proposed storm sewer and the existing gas main, which required relocation of gas facilities by Alliant staff. The landscaping subcontractor finished the terrace restoration on the Henry and Giles Street project area.
  • Friday – The general contractor spent the day organizing materials and removing concrete and sidewalk in preparation for roadway the following week. Crews also spent time moving equipment and materials to the Brickson and Manilla Street project area. The landscaping subcontractor was present on the Park and Lynn Street project area performing terrace restoration.

Work Anticipated for the week of: 7/31/17 – 8/4/17
  • Harrison, Park/Lynn, and Henry/Giles
    • Paving crews have expressed interest in completing the final surface work this week. An effort will be made to review this intention early next week and notification to residents prior to paving will be provided.
  • Division Street
    • Complete water main connection at the Division and North Street intersection after a safe water sample has been obtained and pressure testing has been successful.
    • Complete installation of Inlets 7.2, 7.3, 7.4, and their associated pipe runs after completion of water main connection.
    • Subgrade crews will begin on Tuesday working from the North end of Division Street. Crews will be excavating roadway and placing gravel. Access to driveways will be difficult during daytime activities. Alternative off project parking should be anticipated. Access to driveways will be restored at each days end.
  • Brickson/Manilla Street
    • Utility crews will begin with water main work starting near the Manilla and Forton Street intersection. Water main outage associated with the connection is planned for Monday morning and the affected properties have been notified by the contractor.
 
Monday, July 24, 2017
Construction Update - Week 14
Work completed for the week of: 7/14/17 – 7/21/17
  • Monday –The general contractor mobilized equipment to the Division Street project area. No utility work or removals occurred on Division Street. The landscaping subcontractor was present on Harrison Street performing terrace restoration.
  • Tuesday – The general contractor installed erosion control and removed asphalt pavement at the Division Street project area. The landscaping subcontractor was present at the Harrison Street project area performing terrace restoration.
  • Wednesday – The general contractor started with storm sewer installation at the Division Street project area by installing the new outfall and inlets location North of the Forton Street bridge. The landscaping subcontractor was present at the Henry Street project area. Strong storms brought heavy rainfall accumulation to the area late that night.
  • Thursday – No work occurred at either of the project locations.
  • Friday – The general contractor continued with storm sewer installation by installing the new outfall located South of the Forton Street bridge. No restoration crews were present at either available project area.

Work Anticipated for the week of: 7/24/17 – 7/28/17
  • Park, Henry, and Giles Street
    • Landscaping crews will continue with terrace restoration (weather permitting).
  • Division Street
    • Storm sewer installation along Division Street will continue early in the week.
    • Water main installation at the Division and North Street intersection will occur during the middle part of the week.
    • Subgrade work on the Northern portion of Division Street between the boathouse and the North Street intersection may occur later in the week.
 
Friday, June 16, 2017
Construction Update - Week 9
Work completed for the week of: 6/12/17 – 6/16/17
  • Monday – Concrete work on Harrison Street started with placement of string line and gravel grade preparation between the Main and Hamilton Street intersection. No work occurred on the Park, Henry, or Giles Street project areas.
  • Tuesday – Concrete work on Harrison Street resumed with installation of the curb and gutter between the Main and Hamilton Street. The general contractor started with terrace grading site cleanup at the Park, Henry, and Giles Street project areas.
  • Wednesday – Concrete work on Harrison Street resumed with sidewalk form placement and grading. The general contractor completed manhole and water valve casting adjustments at the Park, Henry, and Giles Street project areas. They also adjusted water service curb stop boxes and continued with terrace grading and site cleanup. Storms brought heavy rains and stopped work early in the afternoon.

  • Thursday – Concrete work on Harrison Street resumed with installation of sidewalk between the Main and Hamilton Street Intersection. The general contractor continued terrace grading and site cleanup at the Park, Henry, and Giles Street project areas.
  • Friday – Concrete work on Harrison Street resumed with sidewalk form placement and grading. Crews resumed with sidewalk, ramp, and apron installation between the Main and Hamilton Street Intersection. The general contractor continued terrace grading and site cleanup at the Park, Henry, and Giles Street project areas.

Work Anticipated for the week of: 6/19/17 – 6/23/17
  • Park, Henry, and Giles Street
    • The general contractor will continue with terrace grading early in the week.
    • Asphalt saw cutting of roadway pavement at the project limits is scheduled to occur Monday afternoon.
    • Asphalt subcontractor will begin road grading later in the week. Binder paving is anticipated to occur early the week of the 26th.
  • Harrison Street
    • The general contractor will continue with terrace grading early in the week.
    • Asphalt saw cutting of roadway pavement at the project limits is scheduled to occur Monday afternoon.
    • Asphalt subcontractor will begin road grading later in the week. Binder paving is anticipated to occur early the week of the 26th.
 
Friday, June 16, 2017
Construction Update - Weeks 6-8
Work completed for the week of: 5/22/17 – 5/26/17
  • Monday – The general contractor continued with road building on Henry Street working North towards the Ridge Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.
  • Tuesday – The general contractor completed the remaining road building on Henry Street. Approval to continue with full street replacement on Giles Street was approved and they started with road building on Giles Street. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.
  • Wednesday – The general contractor continued with road building on Giles Street working West towards the Morris Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.
  • Thursday – The general contractor completed the remaining road building work on Giles Street. They also started with road building on Harrison Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.
  • Friday – The general contractor continued with road building on Harrison Street working North towards the Patterson Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.


Work completed for the week of: 5/29/17 – 6/2/17
  • Monday – No work occurred, Memorial day.
  • Tuesday – The general contractor continued with road building on Harrison Street working North towards the Hamilton Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews excavated to remove the repair sleeve and conduct a more appropriate repair in conjunction with the adjacent hydrant abandonment near the Harrison and Hamilton Street intersection.
  • Wednesday – The concrete subcontractor started with placement of string line for curb and gutter and gravel preparation at the Park, Henry, and Giles Street project areas. The general contractor completed the remaining road building work on Harrison Street.
  • Thursday – The concrete subcontractor continued with placement of string line for curb and gutter and gravel preparation at the Park, Henry, and Giles Street project areas.
  • Friday – The concrete subcontractor started with installation of curb and gutter on the Park, Henry, and Giles Street project areas. Curb work on Park Street was nearly completed with the exception of a few small curb patch section at the Academy intersection. Curb work on Henry and Giles was nearly completed with the exception of the valley gutter work at the two intersections.


Work completed for the week of: 6/5/17 – 6/9/17
  • Monday – The concrete subcontractor setup forms in preparation of the valley gutter work on Henry Street. Crews also started with placement of forms for sidewalk on Park, Henry, and Giles Street. The general contractor started terrace and sidewalk grading on Harrison Street.
  • Tuesday – The concrete subcontractor poured the valley gutters on Henry Street. Crews started with sidewalk, ramp, and apron pour on Henry Park, Henry, and Giles Street. The general contractor continued with terrace and sidewalk grading on Harrison Street.
  • Wednesday – The concrete subcontractor continued to setup forms for sidewalk, ramps, and aprons at the Park, Henry, and Giles Street project areas.
  • Thursday – The concrete subcontractor continued with sidewalk, ramp, and apron pours on Park, Henry, and Giles Street. Crews setup sidewalk forms for the sidewalk meandering through the City park along the South side of Park Street
  • Friday – The concrete subcontractor continued with sidewalk, ramp, and apron pours on Park, Henry, and Giles Street. Crews poured the sidewalk meandering through the City park along the South side of Park Street.
 
Monday, May 22, 2017
Construction Update - Week 5
Work completed for the week of: 5/15/17 – 5/19/17
  • Monday – Utility crews on Harrison Street continued with sanitary sewer installation. Utility crews on Giles Street started with water service replacements.
  • Tuesday – Utility crews on Harrison Street continued with sanitary sewer installation. Crews completed the mainline work after connecting to the existing manhole at the Hamilton Street intersection. Utility crews on Giles Street continued with water service replacements.
  • Wednesday – Utility crews on Harrison Street started with sanitary lateral replacements in the morning. Utility crews on Henry and Giles Street completed the final water main connection at the Giles and Morrison intersection as well as abandoned the last remaining portion of existing water main. All work was halted promptly before noon after wet weather dominated the remainder of the workday.
  • Thursday – Utility crews on Harrison Street installed the new fire hydrant near the Hamilton Street intersection as well as the new main and fire hydrant at the Patterson Street intersection. Road crews began subgrade work on Park Street near the Main Street intersection. Unsuitable subgrade materials were encountered and subgrade stabilization methods were employed.
  • Friday – Utility crews on Harrison continued with began water service and continued sanitary lateral replacements. Road crews on Park Street continued with subgrade work near the Giles Street intersection.

Work Anticipated for the week of: 5/22/17 – 5/26/17
  • Park Street
    • No work is anticipated to occur.
  • Henry/Giles Street
    • Road and sidewalk subgrade work will continue throughout the week.
  • Harrison Street
    • Sanitary lateral and water service replacements will continue through the early part of the week.
    • Final water main connections and abandonments will be scheduled to occur this week.
    • Road and sidewalk subgrade work will begin late in the week.
 
Monday, May 15, 2017
Construction Update - Week 4
Work completed for the week of: 5/8/17 – 5/12/17
  • Monday – Utility crews on Park Street abandoned the existing water main along Park Street and installed San MH-8 at the Academy Street intersection. Utility crews on Giles Street began water main installation starting at the Morris Street intersection. They installed the new fire hydrant at the Southeast corner of the intersection.
  • Tuesday – Road crews continued with road building on Park Street. Unsuitable subgrade material was encountered and road stabilization methods were employed. Utility crews continued with water main installation working East along Giles Street.
  • Wednesday – Road crews continued with road building on Park Street. Unsuitable subgrade material was encountered and road stabilization methods were employed. Utility crews began water service and sanitary lateral replacements on Henry Street. Utility crews began sanitary sewer replacement on Harrison Street and installed San MH 0 and 1.
  • Thursday – Road crews continued with road building on Park Street. Crews continued placement of road base in preparation of curb and gutter installation. Utility crews on Giles Street made the water main connection to the existing main on the East side of the Henry Street intersection. Utility crews began water service and sanitary lateral replacements on Henry Street. Utility crews continued with sanitary sewer replacement working North along Harrison Street.
  • Friday – Utility crews on Henry Street continued with sanitary sewer lateral replacements. Utility crews continued with sanitary sewer replacement working North along Harrison Street.

Work Anticipated for the week of: 5/15/17 – 5/19/17
  • Park Street
    • Subgrade work is expected to occur early in the week.
    • Curb crews may arrive mid to late week to prepare for curb and gutter. Notification will be provided to residents regarding pour curb pour.
  • Henry/Giles Street
    • Sanitary sewer and water service replacements will continue on both Streets.
    • Subgrade work is expected to occur later in the week.
  • Harrison Street
    • Sanitary sewer replacement will continue as crews work towards the Hamilton Street Intersection.
    • Water main connection and fire hydrant installation at the Harrison and Patterson intersection.
    • Sanitary lateral and water service replacements will begin mid to late week.
 
Monday, May 08, 2017
Construction Update - Week 3
Work completed for the week of: 5/1/17 – 5/5/17
  • Monday – Water main replacement resumed on Henry Street and the utility crews were able to complete the water main connection at the Henry and Main Street intersection. Utility crews on Lynn Street completed the remaining sanitary sewer replacement after connecting the existing manhole South of the Park Street intersection.
  • Tuesday – Utility crews on Park Street made the water main connection at the Park and Lynn Street intersection. The crews also started with sanitary sewer lateral and water service replacements. Utility crews on Henry Street started with sanitary sewer replacement working West along Giles Street.
  • Wednesday – Utility crews on Park Street continued with sanitary sewer and water service replacement. Utility crews on Giles Street continued with sanitary sewer replacement.
  • Thursday – Utility crews on Park Street continued with sanitary sewer and water service replacement. Utility crews on Giles Street continued with sanitary sewer replacement. Crews completed sanitary sewer replacement after installing San MH-11.
  • Friday – Utility crews on Park Street completed the abandonment of the existing water main along Park Street by capping the existing main at the Academy Street intersection. Crews also installed San MH-8 and abandoned the existing sanitary sewer along Park Street. Utility crews started with water main replacement on Giles Street working East from the Morris Street intersection. Crews installed the new fire hydrant at the Southeast corner of the intersection.

Work Anticipated for the week of: 5/8/17 – 5/12/17
  • Park Street
    • Subgrade work is expected to occur early in the week.
    • Curb crews may arrive later in the week to prepare for curb and gutter.
  • Henry/Giles Street
    • Water main work will continue on Giles Street between the Morris and Henry Street intersections.
    • Sanitary sewer and water service replacements will be conducted along Henry Street. Water service replacements along Henry Street will be conducted later in the week.
    • Subgrade work is expected to occur later in the week.
 
Monday, May 01, 2017
Construction Update - Week 2
Work completed for the week of: 4/24/17 – 4/28/17
  • Monday – Sanitary sewer replacement resumed on Henry Street. Utility crews on Henry Street installed MH San-10. Once finished with the manhole installation, utility crews made a connection to the existing water main in the Henry and Ridge Street intersection. Water main replacement resumed on Park Street. Utility crews installed the new fire hydrant mid-block along the South side of Park Street.
  • Tuesday – Water main replacement resumed on both Henry Street and Park Street. Utility crews on Henry Street completed water main installation to the Giles Street intersection. Utility crews on Park Street completed water main installation to the Lynn Street intersection. Once finished with water main installation, utility crews began installation of sanitary sewer South along Lynn Street.
  • Wednesday – Utility crews for both Park and Henry Street were able to work for a couple hours early in the day before being rained out the remainder of the workday.
  • Thursday – No work occurred due to wet weather. Water main connection at the Main and Henry Street intersections has been rescheduled to Monday morning.
  • Friday – Water main replacement resumed on Henry Street and sanitary sewer replacement resumed on Lynn Street.

Work Anticipated for the week of: 5/1/17 – 5/5/17
  • Park Street
    • Sanitary sewer replacement South along Lynn Street will continue early in the week.
    • Water service and sewer lateral replacements along Park Street will start early in the week.
  • Henry/Giles Street
    • Water main work will begin on Henry Street on Monday. A connection at the Main Street Intersection will occur on Monday morning.
    • New water main and sanitary sewer installation will begin on Giles Street early in the week.
 
Tuesday, April 25, 2017
Construction Update - Week 1
Work completed for the week of: 4/17/17 – 4/21/17
  • Monday – Sanitary sewer replacement began on both Park Street and Henry Street. Utility crews on Park Street installed MH San-7 at the Academy Street Intersection and proceeded with installation of new sanitary sewer working West along Park Street. Utility crews on Henry Street connected to the existing sanitary manhole at the North side of the Main Street Intersection and proceeded with installation of new sanitary sewer working North along Henry Street.
  • Tuesday – Sanitary sewer replacement resumed on both Park Street and Henry Street. Utility crews on Park Street installed MH San-6.
  • Wednesday – Sanitary sewer replacement resumed on both Park Street and Henry Street. Utility crews on Henry Street installed MH San-9.
  • Thursday – Sanitary sewer replacement resumed on both Park Street and Henry Street. The utility crews on Park Street reached the Lynn Street intersection and completed sanitary sewer installation after installing MH San-4 and 5. The utility crews finished the day short of MH San-10.
  • Friday – Water main replacement began on Park Street. Utility crews made connection to the existing water main in the Academy Street Intersection and proceeded with new water main installation working West along Park Street. Crews installed the new fire hydrant at the Southwest corner of the intersection.


Work Anticipated for the week of: 4/24/17 – 4/28/17
  • Park Street
    • Water main work will resume on Monday. Utility crews will be working West along Park Street.
    • Sanitary sewer replacement South along Lynn Street is being considered and pending approval will begin near the end of the week.
  • Henry/Giles Street
    • Water main work will begin on Henry Street on Monday. A connection at the Ridge Street Intersection will occur followed by utility crews installing new water main working South along Henry Street.
    • New water main and sanitary sewer installation will begin on Giles Street near the end of the week.
 
top