SU Logo
SU Logo
true
home  > Our Community > Construction Project Updates
Construction Project Updates
Select a project to view the status updates. Please note that only Stoughton Utilities lead projects that have a significant impact on residents are listed. For more information about any past, ongoing, or planned construction projects, please contact us.
  
2018 Street and Utility Construction - Forrest, Gjertson, Vernon, Franklin
Updates on Current Stoughton Utilities Construction Projects
Tuesday, July 10, 2018
Week 7 Project Update
Work completed for the week of: 7/2/18-7/6/18
  • Monday – Tri-County on site to pave both binder and surface on Gjertson and Forrest Street. Both streets still closed to ensure that the asphalt cools before traffic is allowed. Utility crew was started sanitary work on Henry Street from the Vernon Street intersection north to the new manhole.
  • Tuesday – The utility crew continued work on Henry Street and installed new manhole. Once manhole was placed, crew started to install the new water services on Vernon Street.
  • Wednesday – Holiday, no work.
  • Thursday – The utility crew installed the sanitary sewer on Morris Street. A second crew was on site to start grading Vernon Street from Academy to Franklin. Guidelines was on site to paint the pavement markings on Gjertson and Forrest Street.
  • Friday – The utility crew continued to install water services and sanitary laterals along Vernon Street. The grading crew installed stop signs on Gjertson and Forrest Street. Landscapers on site to place topsoil and seed in areas that washed out. Both roads open to traffic.

Work Anticipated for the week of: 7/9/18-7/13/18
  • The contractor will continue work on Vernon Street with installation of water services and sanitary laterals. Grading crews will continue to grade the west end of Vernon Street. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Sunday, July 01, 2018
Week 6 Project Update
Work completed for the week of: 6/25/18 - 6/29/18
  • Monday – The contractor was on site on Vernon starting to install sanitary sewer from the Henry Street intersection west. Cattell was on site to pour the concrete driveway aprons and colored concrete ramps on Forrest Street.
  • Tuesday – The contractor was on site on Vernon Street continuing to install sanitary sewer and also flushed and took a water sample of the water main that was installed last week (6/19). A second crew was on site on Gjertson Street starting to install the retaining wall on the north end of the street.
  • Wednesday – The utility crew continued to install sanitary sewer on Vernon Street. Cattell was on site on Forrest pouring the concrete tree grates, concrete terrace, and concrete burb for the new railing next to the hair salon. The wall crew continued to install the retaining wall on Gjertson Street.
  • Thursday – The utility contractor continued to install sanitary sewer on Vernon Street. Cattell was on site pouring the remaining colored concrete on Forrest Street. A second crew was on Forrest Street adjusting castings and grading the South Alley in preparation for paving on Monday (7/2). The landscapers were on site on both Forrest and Gjertson Street placing seed, topsoil and mulch. The wall crew continued to install the retaining wall.
  • Friday – The utility crew completed the sanitary sewer on Vernon Street. The second crew fine graded and proof rolled Forrest Street/South Alley in preparation for paving on Monday. The crew then started fine grading on Gjertson Street in preparation for paving Monday (7/1). The landscapers were on site on both Forrest and Gjertson Street placing seed, topsoil and mulch. The wall crew completed the retaining wall on Gjertson.
    Will work tomorrow (6/30) to complete the fine grading and proof roll of Gjertson Street.

Work Anticipated for the week of: 7/2/18-7/6/18
  • Paving both the binder and surface is scheduled for Monday (7/2) for both Forrest and Gjertson Street. Pavement striping is scheduled for later in the week.
  • The contractor will continue work on Vernon Street with installation of sanitary sewer on Henry Street and Morris Street. Once that is complete, the crew will start to install the new water services on Vernon Street. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Thursday, June 28, 2018
Week 5 Project Update
Work completed for the week of: 6/18/18 - 6/22/18
  • Monday – Contractor on site at Vernon Street installing water main starting at the Academy Street intersection and working east. Cattell on site on Gjertson Street to finish pouring sidewalk and form the 24” valley gutter near Dollar General.
  • Tuesday – No work due to rain.
  • Wednesday – Contractor on site to continue installing 8” watermain on Vernon Street. Cattell on site to form sidewalk on Forrest Street in preparation to pour sidewalk on Friday (6/22).
  • Thursday – No work on Vernon Street or Forrest Street due to rain. Crew on site at Gjertson Street to adjust the sanitary manhole.
  • Friday – Contractor on site to continue 8” water main on Vernon Street. Cattell on site to pour the sidewalk and ramps on Forrest Street as well as some of the area by Dollar General on Gjertson Street.
  • Saturday – Cattell on site to continue pouring on Forrest Street and complete the pour on Gjertson Street near Dollar General.

Work Anticipated for the week of: 6/25/18-6/29/18
  • The contractor will pour colored concrete at Forrest Street early in the week along with driveway aprons on Forrest Street. The retaining wall on Gjertson Street is anticipated to be installed early to middle of the week. Contractor will continue to fine grade on Gjertson Street and Forrest Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will continue work on Vernon Street with sanitary sewer starting at the Henry Street intersection heading west along Vernon. The crew will be removing asphalt and parts of the curb and gutter while installing the sanitary sewer. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Monday, June 18, 2018
Week 4 Project Update
Work completed for the week of: 6/11/18 - 6/15/18
  • Monday – The contractor formed sidewalk on Gjertson Street in preparation for sidewalk pouring later in the week. A second utility crew was placing traffic control and starting to strip asphalt on Vernon Street.
  • Tuesday – The contractor was on site at Forrest Street adjusting inlet castings in preparation for curb being poured on Wednesday. The second utility crew started sanitary installation on Vernon Street.
  • Wednesday – Curb was poured on Forrest Street and some sidewalk poured on Gjertson Street. The second utility crew continued to install new sanitary sewer on Vernon Street.
  • Thursday – Contractor on site at Gjertson Street finishing forming the sidewalk. The second utility crew continued to install new sanitary sewer on Vernon and Franklin Street.
  • Friday – No work on Gjertson Street. The second utility crew completed sanitary sewer on Franklin Street.

Work Anticipated for the week of: 6/18/18-6/22/18
  • The contractor will pour sidewalk, driveway aprons, and curb ramps early to middle of the week on Gjertson Street. Sidewalk and driveway aprons are anticipated to be poured later in the week on Forrest Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will continue work on Vernon Street with water main starting at the Academy Street intersection. The crew will be removing asphalt and parts of the curb and gutter while installing water sewer starting at the Academy Street intersection. Sanitary sewer will be continued on Vernon Street near the Henry Street intersection later in the week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, June 13, 2018
Week 3 Project Update
Work completed for the week of: 6/4/18 - 6/8/18
  • Monday – The contractor completed subgrade work on Gjertson Street. A second utility crew continued to work on subgrade work on Forrest Street.
  • Tuesday – The contractor completed the curb basecourse work Gjertson Street in preparation for curb to be poured on Thursday. A second utility crew installed the last inlet and continued with subgrade work on Forrest Street.
  • Wednesday – Final grading on Gjertson Street in preparation for curb. A second crew was on Forrest Street completing the concrete removals near Main Street.
  • Thursday – Curb was poured on Gjertson Street.
  • Friday – No work on Gjertson Street. A crew continued basecourse work on Forrest Street.

Work Anticipated for the week of: 6/11/18-6/15/18
  • The contractor will pour sidewalk, driveway aprons, and curb ramps early to middle of the week on Gjertson Street. Curb and gutter is anticipated to be poured later in the week on Forrest Street. Continuing of basecourse work on Forrest Street. Access will be restored at the end of each work day.
  • The contractor will start work on Vernon Street on Monday. The crew will be removing asphalt and parts of the curb and gutter while installing sanitary sewer starting at the Academy Street intersection. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, June 06, 2018
Week 2 Project Update
Work completed for the week of: 5/29/18 - 6/1/18
  • Monday – No work, Memorial Day.
  • Tuesday – The contractor started subgrade work on Gjertson Street. A second utility crew continued with sanitary sewer installation in the alley on Forrest Street.
  • Wednesday – No work, rain day.
  • Thursday – The contractor continued with subgrade work on Gjertson Street. The second crew completed storm sewer installation on Forrest Street.
  • Friday – The contractor continued subgrade work on Gjertson Street. The second utility crew started subgrade work on Forrest St.

Work Anticipated for the week of: 6/4/18-6/8/18
  • The contractor will continue subgrade work on both Gjertson Street and Forrest Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will start grading curb and gutter on both Gjertson and Forrest Street. Curb and gutter is anticipated to be early in the week on Gjerston Street and late in the week on Forrest St. At times driveway access may not be available. Access will be restored at the end of each work day.
 
Wednesday, June 06, 2018
Week 1 Project Update
Work completed for the week of: 5/21/18 - 5/25/18
  • Monday – The contractor mobilized to both the Gjertson and Forrest Street project areas. Traffic control and erosion control devices were provided. The contractor performed pavement removals on both streets ahead the next days anticipated utility work.
  • Tuesday – The contractor started with storm sewer installation on Gjertson Street. A second utility crew started with sanitary sewer installation on Forrest Street.
  • Wednesday – The contractor continued with storm sewer installation on Gjertson Street. The second crew continued with sanitary sewer installation on Forrest Street.
  • Thursday – The contractor continued with storm sewer installation on Gjertson Street and installed the new Fire hydrant on the South end of Gjertson Street. The second crew continued with sanitary sewer installation on Forrest Street. Much time was devoted to the installation of sanitary sewer extending East into the alley East of Forrest Street. The excavation and crossing of the many utilities in this area complicated the work.
  • Friday – The contractor on Gjertson Street started installation of the new water service and sanitary sewer laterals to the 208 Van Buren Street property. They also performed the lowering of the existing water service for the 117 Gjertson Street property. The second utility crew continued with sanitary sewer installation in the alley East of Forrest Street.

Work Anticipated for the week of: 5/28/18-6/1/18
  • The contractor will start subgrade work on Gjertson Street. At times driveway access may not be available. Access will be restored at the end of each work day.
  • The contractor will continue with sanitary sewer installation in the alley East of Forrest Street. Storm sewer installation at the Forrest and Jefferson Street intersection will begin early in the week followed with the start of subgrade work later in the week. At times driveway access may not be available. Access will be restored at the end of each work day.
 
top