SU Logo
SU Logo
home  > Our Community > Construction Project Updates
Construction Project Updates
Select a project to view the status updates. Please note that only Stoughton Utilities lead projects that have a significant impact on residents are listed. For more information about any past, ongoing, or planned construction projects, please contact us.
  
2017 Street and Utility Construction
Updates on Current Stoughton Utilities Construction Projects
Friday, June 16, 2017
Construction Update - Week 9
Work completed for the week of: 6/12/17 – 6/16/17
  • Monday – Concrete work on Harrison Street started with placement of string line and gravel grade preparation between the Main and Hamilton Street intersection. No work occurred on the Park, Henry, or Giles Street project areas.
  • Tuesday – Concrete work on Harrison Street resumed with installation of the curb and gutter between the Main and Hamilton Street. The general contractor started with terrace grading site cleanup at the Park, Henry, and Giles Street project areas.
  • Wednesday – Concrete work on Harrison Street resumed with sidewalk form placement and grading. The general contractor completed manhole and water valve casting adjustments at the Park, Henry, and Giles Street project areas. They also adjusted water service curb stop boxes and continued with terrace grading and site cleanup. Storms brought heavy rains and stopped work early in the afternoon.

  • Thursday – Concrete work on Harrison Street resumed with installation of sidewalk between the Main and Hamilton Street Intersection. The general contractor continued terrace grading and site cleanup at the Park, Henry, and Giles Street project areas.
  • Friday – Concrete work on Harrison Street resumed with sidewalk form placement and grading. Crews resumed with sidewalk, ramp, and apron installation between the Main and Hamilton Street Intersection. The general contractor continued terrace grading and site cleanup at the Park, Henry, and Giles Street project areas.

Work Anticipated for the week of: 6/19/17 – 6/23/17
  • Park, Henry, and Giles Street
    • The general contractor will continue with terrace grading early in the week.
    • Asphalt saw cutting of roadway pavement at the project limits is scheduled to occur Monday afternoon.
    • Asphalt subcontractor will begin road grading later in the week. Binder paving is anticipated to occur early the week of the 26th.
  • Harrison Street
    • The general contractor will continue with terrace grading early in the week.
    • Asphalt saw cutting of roadway pavement at the project limits is scheduled to occur Monday afternoon.
    • Asphalt subcontractor will begin road grading later in the week. Binder paving is anticipated to occur early the week of the 26th.
 
Friday, June 16, 2017
Construction Update - Weeks 6-8
Work completed for the week of: 5/22/17 – 5/26/17
  • Monday – The general contractor continued with road building on Henry Street working North towards the Ridge Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.
  • Tuesday – The general contractor completed the remaining road building on Henry Street. Approval to continue with full street replacement on Giles Street was approved and they started with road building on Giles Street. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.
  • Wednesday – The general contractor continued with road building on Giles Street working West towards the Morris Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.
  • Thursday – The general contractor completed the remaining road building work on Giles Street. They also started with road building on Harrison Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.
  • Friday – The general contractor continued with road building on Harrison Street working North towards the Patterson Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.


Work completed for the week of: 5/29/17 – 6/2/17
  • Monday – No work occurred, Memorial day.
  • Tuesday – The general contractor continued with road building on Harrison Street working North towards the Hamilton Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews excavated to remove the repair sleeve and conduct a more appropriate repair in conjunction with the adjacent hydrant abandonment near the Harrison and Hamilton Street intersection.
  • Wednesday – The concrete subcontractor started with placement of string line for curb and gutter and gravel preparation at the Park, Henry, and Giles Street project areas. The general contractor completed the remaining road building work on Harrison Street.
  • Thursday – The concrete subcontractor continued with placement of string line for curb and gutter and gravel preparation at the Park, Henry, and Giles Street project areas.
  • Friday – The concrete subcontractor started with installation of curb and gutter on the Park, Henry, and Giles Street project areas. Curb work on Park Street was nearly completed with the exception of a few small curb patch section at the Academy intersection. Curb work on Henry and Giles was nearly completed with the exception of the valley gutter work at the two intersections.


Work completed for the week of: 6/5/17 – 6/9/17
  • Monday – The concrete subcontractor setup forms in preparation of the valley gutter work on Henry Street. Crews also started with placement of forms for sidewalk on Park, Henry, and Giles Street. The general contractor started terrace and sidewalk grading on Harrison Street.
  • Tuesday – The concrete subcontractor poured the valley gutters on Henry Street. Crews started with sidewalk, ramp, and apron pour on Henry Park, Henry, and Giles Street. The general contractor continued with terrace and sidewalk grading on Harrison Street.
  • Wednesday – The concrete subcontractor continued to setup forms for sidewalk, ramps, and aprons at the Park, Henry, and Giles Street project areas.
  • Thursday – The concrete subcontractor continued with sidewalk, ramp, and apron pours on Park, Henry, and Giles Street. Crews setup sidewalk forms for the sidewalk meandering through the City park along the South side of Park Street
  • Friday – The concrete subcontractor continued with sidewalk, ramp, and apron pours on Park, Henry, and Giles Street. Crews poured the sidewalk meandering through the City park along the South side of Park Street.
 
Monday, May 22, 2017
Construction Update - Week 5
Work completed for the week of: 5/15/17 – 5/19/17
  • Monday – Utility crews on Harrison Street continued with sanitary sewer installation. Utility crews on Giles Street started with water service replacements.
  • Tuesday – Utility crews on Harrison Street continued with sanitary sewer installation. Crews completed the mainline work after connecting to the existing manhole at the Hamilton Street intersection. Utility crews on Giles Street continued with water service replacements.
  • Wednesday – Utility crews on Harrison Street started with sanitary lateral replacements in the morning. Utility crews on Henry and Giles Street completed the final water main connection at the Giles and Morrison intersection as well as abandoned the last remaining portion of existing water main. All work was halted promptly before noon after wet weather dominated the remainder of the workday.
  • Thursday – Utility crews on Harrison Street installed the new fire hydrant near the Hamilton Street intersection as well as the new main and fire hydrant at the Patterson Street intersection. Road crews began subgrade work on Park Street near the Main Street intersection. Unsuitable subgrade materials were encountered and subgrade stabilization methods were employed.
  • Friday – Utility crews on Harrison continued with began water service and continued sanitary lateral replacements. Road crews on Park Street continued with subgrade work near the Giles Street intersection.

Work Anticipated for the week of: 5/22/17 – 5/26/17
  • Park Street
    • No work is anticipated to occur.
  • Henry/Giles Street
    • Road and sidewalk subgrade work will continue throughout the week.
  • Harrison Street
    • Sanitary lateral and water service replacements will continue through the early part of the week.
    • Final water main connections and abandonments will be scheduled to occur this week.
    • Road and sidewalk subgrade work will begin late in the week.
 
Monday, May 15, 2017
Construction Update - Week 4
Work completed for the week of: 5/8/17 – 5/12/17
  • Monday – Utility crews on Park Street abandoned the existing water main along Park Street and installed San MH-8 at the Academy Street intersection. Utility crews on Giles Street began water main installation starting at the Morris Street intersection. They installed the new fire hydrant at the Southeast corner of the intersection.
  • Tuesday – Road crews continued with road building on Park Street. Unsuitable subgrade material was encountered and road stabilization methods were employed. Utility crews continued with water main installation working East along Giles Street.
  • Wednesday – Road crews continued with road building on Park Street. Unsuitable subgrade material was encountered and road stabilization methods were employed. Utility crews began water service and sanitary lateral replacements on Henry Street. Utility crews began sanitary sewer replacement on Harrison Street and installed San MH 0 and 1.
  • Thursday – Road crews continued with road building on Park Street. Crews continued placement of road base in preparation of curb and gutter installation. Utility crews on Giles Street made the water main connection to the existing main on the East side of the Henry Street intersection. Utility crews began water service and sanitary lateral replacements on Henry Street. Utility crews continued with sanitary sewer replacement working North along Harrison Street.
  • Friday – Utility crews on Henry Street continued with sanitary sewer lateral replacements. Utility crews continued with sanitary sewer replacement working North along Harrison Street.

Work Anticipated for the week of: 5/15/17 – 5/19/17
  • Park Street
    • Subgrade work is expected to occur early in the week.
    • Curb crews may arrive mid to late week to prepare for curb and gutter. Notification will be provided to residents regarding pour curb pour.
  • Henry/Giles Street
    • Sanitary sewer and water service replacements will continue on both Streets.
    • Subgrade work is expected to occur later in the week.
  • Harrison Street
    • Sanitary sewer replacement will continue as crews work towards the Hamilton Street Intersection.
    • Water main connection and fire hydrant installation at the Harrison and Patterson intersection.
    • Sanitary lateral and water service replacements will begin mid to late week.
 
Monday, May 08, 2017
Construction Update - Week 3
Work completed for the week of: 5/1/17 – 5/5/17
  • Monday – Water main replacement resumed on Henry Street and the utility crews were able to complete the water main connection at the Henry and Main Street intersection. Utility crews on Lynn Street completed the remaining sanitary sewer replacement after connecting the existing manhole South of the Park Street intersection.
  • Tuesday – Utility crews on Park Street made the water main connection at the Park and Lynn Street intersection. The crews also started with sanitary sewer lateral and water service replacements. Utility crews on Henry Street started with sanitary sewer replacement working West along Giles Street.
  • Wednesday – Utility crews on Park Street continued with sanitary sewer and water service replacement. Utility crews on Giles Street continued with sanitary sewer replacement.
  • Thursday – Utility crews on Park Street continued with sanitary sewer and water service replacement. Utility crews on Giles Street continued with sanitary sewer replacement. Crews completed sanitary sewer replacement after installing San MH-11.
  • Friday – Utility crews on Park Street completed the abandonment of the existing water main along Park Street by capping the existing main at the Academy Street intersection. Crews also installed San MH-8 and abandoned the existing sanitary sewer along Park Street. Utility crews started with water main replacement on Giles Street working East from the Morris Street intersection. Crews installed the new fire hydrant at the Southeast corner of the intersection.

Work Anticipated for the week of: 5/8/17 – 5/12/17
  • Park Street
    • Subgrade work is expected to occur early in the week.
    • Curb crews may arrive later in the week to prepare for curb and gutter.
  • Henry/Giles Street
    • Water main work will continue on Giles Street between the Morris and Henry Street intersections.
    • Sanitary sewer and water service replacements will be conducted along Henry Street. Water service replacements along Henry Street will be conducted later in the week.
    • Subgrade work is expected to occur later in the week.
 
Monday, May 01, 2017
Construction Update - Week 2
Work completed for the week of: 4/24/17 – 4/28/17
  • Monday – Sanitary sewer replacement resumed on Henry Street. Utility crews on Henry Street installed MH San-10. Once finished with the manhole installation, utility crews made a connection to the existing water main in the Henry and Ridge Street intersection. Water main replacement resumed on Park Street. Utility crews installed the new fire hydrant mid-block along the South side of Park Street.
  • Tuesday – Water main replacement resumed on both Henry Street and Park Street. Utility crews on Henry Street completed water main installation to the Giles Street intersection. Utility crews on Park Street completed water main installation to the Lynn Street intersection. Once finished with water main installation, utility crews began installation of sanitary sewer South along Lynn Street.
  • Wednesday – Utility crews for both Park and Henry Street were able to work for a couple hours early in the day before being rained out the remainder of the workday.
  • Thursday – No work occurred due to wet weather. Water main connection at the Main and Henry Street intersections has been rescheduled to Monday morning.
  • Friday – Water main replacement resumed on Henry Street and sanitary sewer replacement resumed on Lynn Street.

Work Anticipated for the week of: 5/1/17 – 5/5/17
  • Park Street
    • Sanitary sewer replacement South along Lynn Street will continue early in the week.
    • Water service and sewer lateral replacements along Park Street will start early in the week.
  • Henry/Giles Street
    • Water main work will begin on Henry Street on Monday. A connection at the Main Street Intersection will occur on Monday morning.
    • New water main and sanitary sewer installation will begin on Giles Street early in the week.
 
Tuesday, April 25, 2017
Construction Update - Week 1
Work completed for the week of: 4/17/17 – 4/21/17
  • Monday – Sanitary sewer replacement began on both Park Street and Henry Street. Utility crews on Park Street installed MH San-7 at the Academy Street Intersection and proceeded with installation of new sanitary sewer working West along Park Street. Utility crews on Henry Street connected to the existing sanitary manhole at the North side of the Main Street Intersection and proceeded with installation of new sanitary sewer working North along Henry Street.
  • Tuesday – Sanitary sewer replacement resumed on both Park Street and Henry Street. Utility crews on Park Street installed MH San-6.
  • Wednesday – Sanitary sewer replacement resumed on both Park Street and Henry Street. Utility crews on Henry Street installed MH San-9.
  • Thursday – Sanitary sewer replacement resumed on both Park Street and Henry Street. The utility crews on Park Street reached the Lynn Street intersection and completed sanitary sewer installation after installing MH San-4 and 5. The utility crews finished the day short of MH San-10.
  • Friday – Water main replacement began on Park Street. Utility crews made connection to the existing water main in the Academy Street Intersection and proceeded with new water main installation working West along Park Street. Crews installed the new fire hydrant at the Southwest corner of the intersection.


Work Anticipated for the week of: 4/24/17 – 4/28/17
  • Park Street
    • Water main work will resume on Monday. Utility crews will be working West along Park Street.
    • Sanitary sewer replacement South along Lynn Street is being considered and pending approval will begin near the end of the week.
  • Henry/Giles Street
    • Water main work will begin on Henry Street on Monday. A connection at the Ridge Street Intersection will occur followed by utility crews installing new water main working South along Henry Street.
    • New water main and sanitary sewer installation will begin on Giles Street near the end of the week.
 
top